Flooring lead times and how to plan around them

Flooring usually sits near the end of a renovation, which is exactly why it gets squeezed. These are our real lead times by service and where the floor should sit in your programme.

Flooring materials stacked and acclimatising in a room before fitting

Lead time by service

These run from order confirmation, and each is followed by prep, acclimatisation and the fit itself. Survey to written quote is 48 hours regardless of service.

  • Luxury vinyl (LVT & SPC): 1–2 weeks
  • Floor restoration & sanding: 1–2 weeks
  • Engineered wood: 2–3 weeks
  • Solid wood: 2–4 weeks
  • Herringbone & parquet: 3–5 weeks

Where flooring belongs in a renovation

After the wet trades and plastering have dried, after first-fix, and generally before skirting so the perimeter detail is clean. In a kitchen, decide early whether the floor runs under the units — it changes the sequence completely and can't be revisited later.

What delays a job

Screed that hasn't dried out is the single most common one; a new screed can hold moisture far longer than people expect and we won't lay over readings that fail. After that: unresolved level changes, thresholds that need joinery, and decisions on finish colour left to the last minute.

Booking around a deadline

Tell us the date the room has to be usable at survey and we'll work backwards through fitting, acclimatisation, drying and delivery to tell you the last safe order date. That's more useful than promising a fast turnaround and missing it.

Frequently asked

Can you ever fit faster?
Sometimes on LVT and restoration, depending on the schedule. We won't compress acclimatisation or drying times to do it.
How long does a new screed need?
Longer than most programmes assume. We test rather than estimate, and the reading decides.
Should the floor go in before or after the kitchen?
It depends on whether the floor runs under the units. Raise it at survey — it affects both the sequence and the cost.
Do you hold materials if my build slips?
Talk to us as soon as you know. Rescheduling early is far easier than moving a booking the week before.

In short

1–2 weeks for LVT and restoration, 2–3 for engineered, 2–4 for solid, 3–5 for parquet, plus prep and acclimatisation. Book from your completion date backwards, and get the screed tested early.

Working to a completion date?

We'll work backwards from your date to the last safe order day.

4.9

Trustpilot

210+

4.9

Google Reviews

140+

9.8/10

Checkatrade

Vetted

BOOK YOUR FREE SURVEY

READY TO
FIT YOUR DREAM FLOOR?

Our flooring experts are here to help. Book a free on-site survey and get a no-obligation quote within 48 hours.

Get Free Quote →